Training, evidence, and tools for battery fire safety
Find out why UL Solutions, CSA Group, Chint Power, Sol-Ark, and other industry leaders trust Atar Fire’s battery fire safety expertise.
Tools
Proven in the Field
Spatial allocation placeholder for a 2-line client quote snippet or field performance metrics.
Interested in training or consulting? Do you have a project you’d like us to review?
Let us know by filling out the form. We’ll get back to you.
Contact Form
Stay Connected
Stay Updated on Battery Fire Safety
Regulations and Field Testing
Newsletter Sign-up
FAQs
Generally, an HMA is required by the 2023 NFPA 855 and the 2024 IFC for installations greater than 600 kWh. The 2026 NFPA 855 lowers this threshold to 20 kWh. Some authorities having jurisdiction (AHJs) require an HMA regardless of the adopted code. Even if an AHJ is unfamiliar with the requirement and does not request an HMA, one may still be legally required, and omitting it can create liability for the system owner and project team. Always check the jurisdiction's code of record to confirm which code edition applies.
An HMA evaluates the potential failure modes of an energy storage system, the measures that prevent those failures, and the measures that reduce their consequences. Codes and standards do not distinguish between product and site HMAs. However, many code requirements are independent of site conditions and depend entirely on the product design. We therefore recommend that the OEM complete a product HMA to confirm the product is properly designed. This streamlines each site HMA and gives the EPC or developer greater assurance that the selected product meets all fundamental product requirements.
An ERP supports first responders and facility staff with pre-incident planning and situational awareness during an incident. It provides critical information about the product, the site, and response procedures. NFPA 855 requires on-site training for the fire department and other relevant stakeholders at the earliest stage of a project (before products arrive on site) and annually thereafter.
An HMA typically takes two to six weeks, depending on backlog and the availability of required input information. Atar Fire assembles project drawings and product information into a draft HMA, which may raise questions about site layout, signage, fire alarm integrations, disconnects, clearances, and similar items. The process is typically iterative: outstanding questions are answered and, where necessary, changes are incorporated into the site design. Requests for additional information or design changes can extend the timeline. Atar Fire works collaboratively with partners to keep the process smooth, achieve a compliant design, and streamline permitting.